Case Studies

Castle Road Construction

FMG Solomon Mine Site required the construction of a new 5.3km all-weather access road, Castle Road, from its permanent mine site camp to the central facilities office and workshop area.

The works involved the installation of multiple groups of corrugated steel pipes to light vehicle roads, the construction of light vehicle roads and the construction of drainage channels.

The construction of Castle Road consisted of clear and grub of topsoil material, cut and backfill material road embankments and the installation of a 200mm wearing course / pavement, surface grading, installation of light vehicle windrow delineators and reinstalling existing road signage along the entire length of the road.

$4.0M

Client

FMG

Location

Solomon Mine Site, WA

Project Duration

5 months

Project Start

April 2021

Project Finish

August 2021

Our Recent Projects

We’re proud of our achievements. Read about our recent projects and case studies to see what we’ve been working on and how we could work with you.

View all projects
Path
Flying Fish Dewatering

FMG’s Eliwana Mine Site required the installation of dewatering infrastructure to allow the mining of the

PathLearn more
Solomon Stockyards 1A TN Pump Install & Tie-Ins

FMG undertook a review of Solomon’s forecasted water balance and identified the requirement to reequip an

PathLearn more
Roy Hill ROM4 Drainage

TCD were engaged by Nepean for delivery of the Roy Hill ROM 4 Marble Bar Road Upgrade Project.  The scope

PathLearn more
Path

Talk to our Civil Construction Experts

We’re a trusted partner for the civil mining and construction industry. Our construction contractors can make your next project a success.

Contact Us