TCD were awarded the Broome North Wastewater Treatment Plant 80ML Storage Dam No. 2 works in June 2023, with an aggressive construction timeline requiring the bulk of the works to be completed ahead of the 2023 northwest wet season.
Key Deliverables:
- 60,000 m³ of bulk and detailed cut to fill earthworks, imported compacted gravel crest and external embankment rock protection works
- 35,000 m² of bituminous geomembrane (BGM) liner installation
- 300 m³ of concrete spillways and BGM tie-ins
- Supply, installation and commissioning of interconnecting pipework and valves between existing Storage Dam No. 1 and new Storage Dam No. 2
- Supply and installation of 15 anchored egress nets
- Installation of 3 specialist sonic drilled piezometer bore holes
- Installation of concrete kerbing and perimeter security fencing