Tag Archives: Pump Stations

Mine Dewatering Pipelines Pump Stations Water Management Read More Carrot icon
graphic graphic
Worker installing pipeline at KCGM Saline Dam

Details

Description
Description

TCD delivered a complete pump station and control infrastructure package for the Saline Dam 3 dewatering system at KCGM’s Super Pit operations in Kalgoorlie. The project integrated portable control buildings with high-capacity pump systems to manage saline water from mining operations.

Our team manufactured and installed custom portable control rooms, complete pump station infrastructure including manifolds and pipework, and integrated electrical and communications systems – delivering a turnkey solution for this critical water management facility.

Key Deliverables
  • Portable control room buildings – manufactured and installed
  • High-capacity pump station with multiple pump units
  • Stainless steel manifold and valve systems
  • Large-diameter pipeline infrastructure
  • Electrical and control system integration
  • Concrete foundations and civil works
Summary
Client
Northern Star Resources / KCGM
Location
Kalgoorlie, WA
Project Duration
6 Months
Project Start
October 2025
Project Finish
Ongoing

Gallery

KCGM pump manifold and pipework
KCGM pump station detail view of equipment
KCGM pump station overview showing complete installation
Crane installing building at KCGM site
KCGM control room interior
Close icon
Featured Modal Image
Pipelines Pump Stations Water Management

Solomon Stockyards 1A TN Pump Install & Tie-Ins

Read More Carrot icon
graphic graphic
Solomon Stockyards 1A TN Pump Install project for Fortescue in Solomon, Pilbara, WA — TCD Group

Details

Description

Fortescue undertook a review of Solomon’s forecasted water balance and identified the requirement to reequip and abstract water from the existing stockyards borefield. This borefield, along with future borefields in the lower Fortescue area would be used to supply up to 250 L/s of water for use throughout the Solomon site.

The existing Solomon Drive Turkeys Nest will be used to store the bore water before being transferred by a new High Pressure (HP) pump station up to the existing Raw Water Break Tank. This transfer will be achieved through a newly installed DN630 HP HDPE pipeline. In addition to this, water will also be gravity fed down to the existing 17M Dam Raw Water Storage Facility (RWSF) via a newly installed DN630 HDPE supplementary gravity main.

TCD’s key deliverables included:

  • Upgrade of stockyards Turkey’s Nest with new electrical pumps and associated steel piping.
  • Cleaning and rectification of existing Turkey’s Nest.
  • Installation of new high-pressure pipes through the pond wall.
  • Installation of new electrical pumps.
  • Installation of new steel pump station, with associated valving.
  • Hydro testing of new pump station and piping.
Summary
Client
FMG
Location
Solomon Mine Site, WA
Project Duration
3 Months
Project Start
September 2022
Project Finish
November 2022

Gallery

Solar-powered pump station and pipeline in a remote, arid landscape — Fortescue project, Solomon, Pilbara, Western Australia. TCD Group civil construction
Pipeline installation with heavy equipment in a rugged landscape — Fortescue project, Solomon, Pilbara, Western Australia. TCD Group civil construction
Worker inspecting equipment next to a trench and pipeline in a rugged landscape — Fortescue project, Solomon, Pilbara, Western Australia. TCD Group civil construction
Solomon Stockyards 1A TN Pump Install project for Fortescue in Solomon, Pilbara, WA — TCD Group
TCD construction project image
TCD construction project image
TCD construction project image
Close icon
Featured Modal Image

Talk to our Construction Experts

We support our clients when they need it most. Contact our experts to see how TCD can partner with your business.