Roy Hill ROM4 Drainage

Read More Carrot icon
graphic graphic

Details

Description

TCD were engaged by Nepean for delivery of the Roy Hill ROM 4 Marble Bar Road Upgrade Project. The scope of work included delivering the following to MRWA specifications:

  • Implementation of MRWA approved traffic management and traffic controls.
  • Survey control establishment and construction set-out.
  • Offshoot drainage formation and upgrades.
  • Box out of existing pavement shoulder.
  • Subgrade preparation.
  • Importation, placing and compacting 125mm crushed rock subbase.
  • Importation, placing and compacting 180mm crushed rock basecourse.
  • Prime and 16/10mm double-double seal with S45R polymer modified binder (PMB) and 7mm scatter coat.
  • Supply and Installation of 600m of TL3 standard guardrail and end terminals.
  • Construction of 60m of concrete TL5 crash barrier as cast in-situ.
Summary

$2.5M

Total Project Cost

Client
Nepean Conveyors
Location
Marble Bar, WA
Project Duration
7 Months
Project Start
September 2022
Project Finish
March 2023

Gallery

Close icon
Featured Modal Image

Talk to our Construction Experts

We support our clients when they need it most. Contact our experts to see how Aaro can partner with your business.

Leave a Reply

Your email address will not be published. Required fields are marked *