We delivered early works and culvert repairs on a haul road at the Eliwana site in the Pilbara for FMG. The project involved stabilising and repairing existing drainage structures to ensure continued operational integrity of the road network. Our scope covered the necessary civil construction activities to prepare the site and restore the culvert functionality. Our approach included comprehensive earthworks, from setting out and site clearing to bulk excavation and backfilling. We managed dewatering and soil erosion control to maintain site stability during construction. The works involved trenching, grading, and compaction to establish proper sub-grade and embankment levels. We adhered to strict site protocols for critical risk management, ensuring all activities were coordinated with client representatives before proceeding.
Key Deliverables
- Culvert repair and early works
- Bulk earthworks and excavation
- Site clearing and grubbing
- Dewatering and erosion control
- Grading and compaction of sub-grade
- Backfilling and site restoration