TCD was engaged to complete the bulk earthworks for the Cloudbreak Solar project, supporting the development of 197 MWdc of solar photovoltaic (PV) generation and large-scale battery storage.
Key Deliverables:
- 350 hectares of clearing and grubbing
- 125 hectares of final trimming works
- Installation of 32 cable culverts
- 25 kilometres of access tracks
- 30,000 m³ of cut/fill
- 13 kilometres of fencing
TCD actively coordinated with Fortescue to deliver the project on time, incorporating significant scope variations while managing interfaces with other contractors to ensure no delays onsite.
Summary
Client
Fortescue
Location
Cloudbreak, WA
Project Duration
5 Months
Project Start
April 2025
Project Finish
August 2025