Emergency Repairs to Rio Tinto Deepdale Line

When a culvert collapsed to create a dangerous void in Rio Tinto’s rail formation, TCD and our Indigenous partner, Yarra, had just three days to replace and complete the repairs. This included cutting of the track, excavation, backfill and relaying of the track

Success for a task like this comes down to planning before any tool is lifted or machine started. We had one day to prepare and two days for the closure of the rail track. The works were completed on time with no further delays to Rio Tinto’s Rail Operations.

Even with careful preparation, things don’t always go to plan. We had a delay when the track wasn’t cut on time. Fortunately, our highly experienced team took it in their stride and the delay didn’t affect the ultimate completion time.

$166K

Client

Rio Tinto

Location

Karratha, WA

Project Duration

2 Days

Project Start

February 2018

Project Finish

February 2018

Our Recent Projects

We’re proud of our achievements. Read about our recent projects and case studies to see what we’ve been working on and how we could work with you.

View all projects
Path
Flying Fish Dewatering

FMG’s Eliwana Mine Site required the installation of dewatering infrastructure to allow the mining of the

PathLearn more
Solomon Stockyards 1A TN Pump Install & Tie-Ins

FMG undertook a review of Solomon’s forecasted water balance and identified the requirement to reequip an

PathLearn more
Roy Hill ROM4 Drainage

TCD were engaged by Nepean for delivery of the Roy Hill ROM 4 Marble Bar Road Upgrade Project.  The scope

PathLearn more
Path

Talk to our Civil Construction Experts

We’re a trusted partner for the civil mining and construction industry. Our construction contractors can make your next project a success.

Contact Us