Case Studies

Surface Water Management & Norfolk Turkey’s Nest

FMG engaged TCD to install several culverts across two new haul roads within their Christmas Creek and Cloudbreak Mine Sites.

Cloudbreak required five culvert locations, with sizes ranging from 600mm diameter to 1,500mm diameter, and a cumulative length of 672m. While over at Christmas Creek there were six locations, with sizes ranging from 900mm diameter to 1,500mm diameter, and a cumulative length of 1,416m.

What started as a straightforward job grew in scope while we were on-site and, thanks to our range of services, we were quickly able to take on additional works, which included Access Track Upgrades and the installation of a Turkey’s Nest.

The works for the 3 ML Turkey’s Nest included the supporting civil pads and access tracks, the installation of geofabric and HDPE liner, float arm, fencing, signage, egress nets, life buoys and conveyor protection matting.

$3.3M

Client

FMG

Location

Pilbara, WA

Project Duration

4 Months

Project Start

July 2018

Project Finish

November 2018

Our Recent Projects

We’re proud of our achievements. Read about our recent projects and case studies to see what we’ve been working on and how we could work with you.

View all projects
Path
Flying Fish Dewatering

FMG’s Eliwana Mine Site required the installation of dewatering infrastructure to allow the mining of the

PathLearn more
Solomon Stockyards 1A TN Pump Install & Tie-Ins

FMG undertook a review of Solomon’s forecasted water balance and identified the requirement to reequip an

PathLearn more
Roy Hill ROM4 Drainage

TCD were engaged by Nepean for delivery of the Roy Hill ROM 4 Marble Bar Road Upgrade Project.  The scope