Flying Fish Dewatering

FMG’s Eliwana Mine Site required the installation of dewatering infrastructure to allow the mining of the Flying Fish ore body. This included a new bore field, pipeline infrastructure, holding tanks and turkey’s nests.

TCD’s key deliverables included:

  • 45km of HDPE pipelines for water supply of the mine, inclusive of 8km of buried pipelines.
  • 4 x Turkey’s Nests, each with a LV and HV Standpipe.
  • 1 x Transfer Pond and Pump Station.
  • 12 x Abstraction Bores.
  • 6 x Re-Injection Bores.

Whilst on-site additional works were awarded for the pipe re-alignment for the Flying Fish Haul Road, as the current design clashed with the existing pipeline.  Works included the installation and re-alignment of piping, valves and fittings.

$18M

Client

FMG

Location

Eliwana Mine Site, WA

Project Duration

12 months

Project Start

June 2022

Project Finish

June 2023

Our Recent Projects

We’re proud of our achievements. Read about our recent projects and case studies to see what we’ve been working on and how we could work with you.

View all projects
Path
Flying Fish Dewatering

FMG’s Eliwana Mine Site required the installation of dewatering infrastructure to allow the mining of the

PathLearn more
Solomon Stockyards 1A TN Pump Install & Tie-Ins

FMG undertook a review of Solomon’s forecasted water balance and identified the requirement to reequip an

PathLearn more
Roy Hill ROM4 Drainage

TCD were engaged by Nepean for delivery of the Roy Hill ROM 4 Marble Bar Road Upgrade Project.  The scope

PathLearn more
Path

Talk to our Civil Construction Experts

We’re a trusted partner for the civil mining and construction industry. Our construction contractors can make your next project a success.

Contact Us